SolarInstallerList
Step-by-Step Guide

Solar Installation Timeline

From first enquiry to generating free electricity, here's exactly what happens during a solar panel installation and how long each stage takes.

4-8

weeks total

Quote to power-on

1-2

days installation

Actual on-site work

10

key steps

From start to finish

0%

VAT until 2027

On residential solar

The Installation Journey

1

Get Quotes & Compare

Research installers, request quotes, and compare options from multiple MCS-certified companies.

1-2 weeks

What Happens

  • Request 3-5 quotes from different installers
  • Compare system sizes, panel brands, and prices
  • Check installer reviews and credentials
  • Ask about warranties and aftercare

Tips

  • Don't just go with the cheapest - quality matters
  • Check MCS certification is current
  • Ask for references from previous customers
2

Site Survey

A surveyor visits your property to assess your roof, electrical system, and design the optimal system.

1-2 hours

What Happens

  • Roof inspection (condition, orientation, shading)
  • Electrical assessment (consumer unit, meter)
  • Measurements and photos for design
  • Discussion of panel placement preferences

Tips

  • Be home for the survey to ask questions
  • Point out any roof issues or access challenges
  • Discuss where you'd like the inverter located
3

Design & Quote Finalisation

Installer creates detailed system design based on survey findings and provides final quote.

1-2 weeks

What Happens

  • System design with panel layout
  • Generation estimates for your specific roof
  • Final pricing including any required upgrades
  • Contract preparation

Tips

  • Review the design carefully
  • Check estimated generation seems realistic
  • Understand what's included in the price
4

DNO Notification

Your installer notifies the Distribution Network Operator (DNO) of the planned installation.

1-4 weeks

What Happens

  • G98 notification for systems up to 3.68kW (simple)
  • G99 application for larger systems (more involved)
  • DNO may request additional information
  • Approval typically received within 4 weeks

Tips

  • Your installer handles this for you
  • Larger systems may take longer to approve
  • This happens while scheduling installation
5

Pre-Installation Prep

Prepare your property for the installation day, including clearing access and parking.

1-2 days before

What Happens

  • Clear the loft/attic if being accessed
  • Ensure scaffolding access is clear
  • Prepare parking space near property
  • Inform neighbours about scaffolding

Tips

  • Ask installer exactly what prep is needed
  • Confirm timing and what to expect
  • Plan for power interruption during commissioning
6

Scaffolding Erection

Scaffolding is installed to provide safe roof access (may be same day or day before main install).

0.5-1 day

What Happens

  • Scaffolders arrive early morning
  • Takes 2-4 hours typically
  • May need access through garden/neighbour
  • Scaffolding stays up until install complete

Tips

  • Secure any valuables in garden sheds
  • Move any fragile plants away from scaffold area
  • Check scaffolding doesn't block essential access
7

Installation Day

The main installation happens - mounting system, panels, inverter, and wiring.

1-2 days

What Happens

  • Team arrives 8-9am typically
  • Roof mounts and rails installed first
  • Panels fixed to mounting system
  • DC wiring run to inverter location
  • Inverter and isolation switches installed
  • Connection to consumer unit

Tips

  • Someone should be home during installation
  • Tea and coffee appreciated by installers!
  • Ask questions as work progresses
8

Electrical Testing & Commissioning

System is tested, connected to the grid, and turned on for the first time.

2-4 hours

What Happens

  • Electrical safety testing
  • System configuration and optimisation
  • First power-on and checks
  • Brief power interruption required
  • Monitoring system setup

Tips

  • Ask for a walkthrough of the system
  • Get shown how to read the inverter
  • Set up monitoring app on your phone
9

Scaffolding Removal

Scaffolding is dismantled and removed, usually the day after installation or same day.

0.5 day

What Happens

  • Takes 2-3 hours typically
  • Final roof check before removal
  • Any garden reinstatement if needed

Tips

  • Check for any minor damage to garden
  • Inspect roof visually after scaffolding gone
  • Report any issues immediately
10

Sign-Off & Documentation

Receive all certificates and documentation, and register for SEG payments.

1-2 weeks

What Happens

  • MCS certificate (essential for SEG)
  • DNO commissioning confirmation
  • Electrical certificates
  • Warranty documentation
  • User manuals

Tips

  • Keep all documents safe
  • Apply for SEG payments promptly
  • Register your system for monitoring

What Can Affect Timing?

May Take Longer

  • Busy season (spring/summer)
  • Larger systems (>3.68kW) need G99 approval
  • Roof repairs needed first
  • Consumer unit upgrade required
  • Listed building or conservation area
  • Complex roof layout

Can Speed Things Up

  • Off-peak season (autumn/winter)
  • Standard size system (<3.68kW)
  • Modern consumer unit in good condition
  • Easy roof access
  • Flexible on installation dates
  • Quick decision making

What to Expect on Installation Day

8:00 AM

Team Arrives

Installers arrive and unload equipment. Brief introduction and walkthrough of the day.

8:30 AM

Roof Work Begins

Mounting brackets and rails installed on your roof. Some noise from drilling.

11:00 AM

Panels Installed

Solar panels are carried up and fixed to the mounting system.

1:00 PM

Lunch Break

Team takes a break. Wiring work begins inside property.

2:00 PM

Inverter Installation

Inverter mounted (usually garage, loft, or utility room). Wiring connected.

3:30 PM

Grid Connection

System connected to consumer unit. Brief power interruption (30-60 mins).

4:30 PM

Testing & Handover

System tested and switched on. Walkthrough of monitoring and controls. Cleanup and departure.

Ready to Start Your Solar Journey?

Get quotes from MCS-certified installers and take the first step towards free, clean electricity.